Long Beach Demolition Permits: The Clearances Behind the Paperwork

Long Beach Demolition Co Team

September 8, 2026 | 7 min read

In Long Beach, a demolition permit is less a single form than the end of a chain of sign-offs. The City's Development Services department, through its Building and Safety Bureau, issues the permit, but several other offices have to be satisfied before it can be released. This article describes the general pattern so you can plan around it. Procedures, bulletins and fees are updated from time to time, so confirm the current checklist with the City before you promise anyone a start date.

Who is involved

The Building and Safety Bureau handles the permit itself, usually through the Development Permit Center. City guidance has generally called for the application to be filed by a California-licensed contractor holding the appropriate classification and a Long Beach business license, so ask any contractor you are comparing to explain how they meet that requirement for your job. A parcel in an adjoining city, or on land controlled by the Port, may answer to a different agency entirely, which is worth settling before anything else.

The departments that typically weigh in

  • Planning Bureau: Demolition applications are generally screened by Planning. Extra rules can apply in a historic district, inside the Coastal Zone, or when dwelling units would be lost. See our separate guide on coastal and historic review.
  • Health and Human Services: Long Beach runs its own city health department, and the municipal code has called for a vector and rodent clearance before a demolition permit is issued. Confirm the current wording and process with the department.
  • Public Works: If a dumpster, fence, equipment or truck staging will occupy the sidewalk or street, right-of-way and pedestrian-protection permits may be needed.
  • Gas and electric providers: Proof that gas has been shut off and capped, and that electric service has been disconnected, is commonly requested. Long Beach Energy Resources and Southern California Edison are the usual contacts, depending on the address.
  • Long Beach Water Department: Water and sewer connections generally need a capping plan, and the department may weigh in on sewer capacity.
  • South Coast AQMD: A copy of the Rule 1403 demolition notification is typically part of the package. We cover the timing in a dedicated article.

When plan review gets heavier

City guidance has described a more formal plan review for larger or more complicated jobs, for example taller structures, basements or subterranean levels of significant depth, buildings sharing a wall with a neighbor, or non-standard demolition methods. Taller or deeper structures can also bring in a Cal/OSHA demolition permit. If your building touches a neighboring structure, ask the City how adjacent-owner notice works, since a waiting period has historically applied unless the neighbor consents in writing.

Sequencing that saves time

Start with the clearances that take the longest and depend on third parties: utility disconnects, the asbestos survey and any Planning question. Paperwork that needs a utility's confirmation cannot be rushed by the contractor. Hold the demolition date open until the permit and the air-district notice both exist. A date set too early tends to be moved, and moving an AQMD start date earlier than notified is itself something the district wants revised. Keep a single folder, digital or paper, with every clearance, receipt and disconnect letter. Inspectors and later closeout steps go faster when it is all in one place.

What usually causes delays

  • Utility shut-off letters that were requested late or never matched to the right meter.
  • An asbestos report that is missing, outdated or does not cover the whole building.
  • A historic-district or Coastal Zone question discovered only after the application is filed.
  • A scope that changes midway, such as a partial demolition becoming a full teardown.

How a contractor fits in

Expect your contractor to tell you in writing which clearances they will chase and which remain yours or your builder's. If a quote is silent on permits, ask. A vague answer now often becomes an argument later.

Thinking about a teardown in Long Beach? Call Long Beach Demolition Co at (562) 210-0343 and we will talk through the clearances for your address.

Plan your Long Beach demolition

Share the address, the scope and your target dates. Long Beach Demolition Co will map out the city clearances, air-district notice and utility steps, then send a written quote.