SCAQMD Rule 1403: The Notification Clock Before a Long Beach Demolition
September 15, 2026 | 6 min read
Long Beach sits inside the South Coast Air Quality Management District, and the district's Rule 1403 is the one that most often sets the pace of a demolition schedule here. It governs how asbestos is surveyed for, reported and handled when buildings are demolished or renovated, and it works alongside the federal Asbestos NESHAP. What follows is a general overview, not legal advice. Check the district's current rule text, forms and fee schedule before you rely on any date.
Notice is needed even with a clean survey
A common misunderstanding is that a survey with no asbestos means no paperwork. Under Rule 1403 as it has been described by the district, notification before demolition is generally expected whether or not asbestos-containing material was found. A clean report changes what must happen on site, not whether the district hears about it.
The lead time
The district has asked for notification roughly ten working days before the demolition begins. Ten working days is about two calendar weeks, longer around holidays. Because the count is in working days, a job that looks comfortably scheduled can end up short once a long weekend is factored in. Confirm the current lead time and how the district counts it.
Typical steps
- Survey first: A qualified inspector looks for suspect materials, samples them and reports results. The survey is expected before demolition or renovation work disturbs anything.
- File the notification: The district has offered an online application. Notifications carry a fee under the district's fee rule, and the amount should be checked on the current schedule.
- Share it with the City: A copy is commonly requested as part of the City of Long Beach demolition permit package.
- Abate if required: Where regulated asbestos-containing material is present above the district's quantity thresholds, removal by properly certified abatement contractors generally comes before the general demolition crew starts.
- Revise when plans shift: If the start date or scope changes, the notification typically has to be revised. Moving a start date earlier than what was filed is the situation that causes the most trouble.
Who can do what
Abatement is a licensed specialty. Contractors who remove larger quantities of asbestos-containing material are expected to hold the appropriate California contractor classification and Cal/OSHA registration or certification. For pre-1978 buildings, lead work may call for separate state certification. Ask for current proof of any credential rather than relying on a verbal assurance.
Dust and wind in a coastal city
Even when nothing is regulated as asbestos, demolition raises dust, and an onshore afternoon breeze can carry it well past a property line. Wetting down, staged knock-down and cleaned truck exits are routine practice. Ask how your contractor plans to handle it, particularly close to neighbors or schools.
Avoiding a schedule slip
- Order the survey before choosing a demolition date.
- File the notification as soon as the survey and scope are settled.
- Agree in writing who files, who pays the fee and who revises if dates move.
- Keep the survey, notification and waste records together for the project file.
Long Beach Demolition Co coordinates surveys and notifications as part of demolition planning. Call (562) 210-0343 to review your property.
Plan your Long Beach demolition
Share the address, the scope and your target dates. Long Beach Demolition Co will map out the city clearances, air-district notice and utility steps, then send a written quote.